Third Party Inspection for Ground Storage Tank-

            Reference Documents- 1.     Design code 2.     Purchase order specification 3.     Purchaser's standards 4.     Approved drawings 5.     API 650 6.     API 620 7.     API 653 8.     BS 2654 Inspection Activities from start to finish-              Material Inspection            Fabrication Inspection            Plate Preparation            Shell Courses and Base Plates containing Welded Seams            Post Weld Heat Treatment of Hot Formed Components            Assembly Inspection             Painting and Coating              ...

Important point for Welding Inspector-SE-2


Typical documents that may need to be referred to are:

  • The Application Standard (or Code)
  • Quality plans or inspection check lists
  • Drawing
  • QC procedures

Guidance and basic requirements for visual inspection are given by:

ISO 17637 (Non-destructive examination of fusion welds - visual Examination)


Conditions for Visual Inspection (to BS EN ISO 17637)-

  •     Illumination-
              350 lux minimum required. (recommends 500 lux - normal shop or office lighting).
  •    Vision access- 
             Eye should be within 600mm of the surface.
             Viewing angle (line from eye to surface) to be not less than 30°.

                                                     
Weld Terminology  Butt Joint

Weld Terminology Fillet Joint

Duties of a welding inspector during Fabrication Process
  • Before welding.
  • During welding.
  • After welding.

Important point for Welding Inspector-(SE-1)





Comments

Popular posts from this blog

Important point for Welding Inspector-(SE-1)

Third Party Inspection for Pressure Vessel –

Radiography Test Film Inspection as per ASME B 31.1

Third Party Inspection for Ground Storage Tank-

Third Party Inspection for Valve - Procedure

Pressure Vessel Inspection as per ASME SEC VIII DIV.1

Third Party Inspection for Shell and Tube Heat Exchanger-

(Importants) ASME and National Board Stamps-