Third Party Inspection for Ground Storage Tank-

            Reference Documents- 1.     Design code 2.     Purchase order specification 3.     Purchaser's standards 4.     Approved drawings 5.     API 650 6.     API 620 7.     API 653 8.     BS 2654 Inspection Activities from start to finish-              Material Inspection            Fabrication Inspection            Plate Preparation            Shell Courses and Base Plates containing Welded Seams            Post Weld Heat Treatment of Hot Formed Components            Assembly Inspection             Painting and Coating              ...

Third Party Inspection for Valve - Procedure

      Reference Documents-
  1. Design code
  2. Purchase order specification
  3. Purchaser's standards
  4. Approved drawings
  5. API 598
  6. API 6D
  7. API 594
  8. ASME / ANSI B16.5
  9. API 600, 602, 603, 604


Following Inspection Activities from Start to Finish-



  • Material Inspection
  • Welding Inspection
  • Post Weld Heat Treatment
  • Visual and Dimensional Checking
  • Low Pressure Air Test
  • Hydrostatic Testing
  • Post Hydrostatic Testing
  • Final Inspection
  • Name Plate Checking
  • Painting and Coating
  • Spare Parts, Loose Items and Accessories
  • Reporting
  • Release Note
  • Packing, Marking and Shipping
  • Final Book (Dossier)

Comments

Popular posts from this blog

Important point for Welding Inspector-(SE-1)

Third Party Inspection for Pressure Vessel –

Radiography Test Film Inspection as per ASME B 31.1

Third Party Inspection for Ground Storage Tank-

Pressure Vessel Inspection as per ASME SEC VIII DIV.1

Third Party Inspection for Shell and Tube Heat Exchanger-

Important point for Welding Inspector-SE-2

(Importants) ASME and National Board Stamps-