Third Party Inspection for Ground Storage Tank-

            Reference Documents- 1.     Design code 2.     Purchase order specification 3.     Purchaser's standards 4.     Approved drawings 5.     API 650 6.     API 620 7.     API 653 8.     BS 2654 Inspection Activities from start to finish-              Material Inspection            Fabrication Inspection            Plate Preparation            Shell Courses and Base Plates containing Welded Seams            Post Weld Heat Treatment of Hot Formed Components            Assembly Inspection             Painting and Coating              ...

Third Party Inspection for Fire Tube Boiler - Procedure

Reference Codes-

  • Design code
  • Purchase order specification
  • Purchaser's standards
  • Approved drawings
  • ASME I
  • ASME V
  • ASME IX
  • BS 2790

Inspection activities for Fire Tube Boiler-(From Start to Finish)

  •  Material Inspection
  •  Fabrication
  •  Post Hydrostatic Test
  •  Final Assembly
  •  Marking
  •  Name Plate Checking
  •  Painting and Coating Inspection
  •  Spares, Loose Items, Tools and Accessories:
  •  Reporting
  •  Release Note
  •  Packing, Marking and Shipping:
  •  Final Book (Dossier).

Documents for Third Party Inspector Review:

  • Manufacture Quality Control Plan 
  • ITP
  • Data Sheet
  •  Approved Drawings
  • Strength calculation sheets
  • Material Test Reports
  • WPS  and PQR
  • Welding Map
  •  Repair Procedure
  • WQR
  • NDE procedures (VT,RT,UT,MPT,DPT and PMI)
  • NDE Personnel qualifications Reports
  • Heat treatment procedure
  • Calibration Certificates for test equipments
  • Hydrostatic Testing Procedure and Water Quality Document
  • Painting Procedure
  • Preservation,Packing and Shipping Procedure 
  • Packing List


      Note-
         Material Inspection (Review following)- on MTC.
  • Certificate No.
  • Heat or cast No.
  • Chemical composition.
  • Mechanical Properties
  • Heat treated condition.
  • NDE applied and results. 


Third Party Inspection for Shell and Tube Heat Exchanger-


Third Party Inspection for Pressure Vessel –


Pressure Vessel Inspection as per ASME SEC VIII DIV.1


Third Party Inspection for Valve - Procedure-


Comments

Popular posts from this blog

Important point for Welding Inspector-(SE-1)

Third Party Inspection for Pressure Vessel –

Radiography Test Film Inspection as per ASME B 31.1

Third Party Inspection for Ground Storage Tank-

Third Party Inspection for Valve - Procedure

Pressure Vessel Inspection as per ASME SEC VIII DIV.1

Third Party Inspection for Shell and Tube Heat Exchanger-

Important point for Welding Inspector-SE-2

(Importants) ASME and National Board Stamps-