Third Party Inspection for Ground Storage Tank-

            Reference Documents- 1.     Design code 2.     Purchase order specification 3.     Purchaser's standards 4.     Approved drawings 5.     API 650 6.     API 620 7.     API 653 8.     BS 2654 Inspection Activities from start to finish-              Material Inspection            Fabrication Inspection            Plate Preparation            Shell Courses and Base Plates containing Welded Seams            Post Weld Heat Treatment of Hot Formed Components            Assembly Inspection             Painting and Coating              ...

Radiography Test Film Inspection as per ASME B 31.1

Radiography Inspection-
Paragraph-136.4.5
When required by this Chapter (see Table 136.4), radiographic examination shall be performed in accordance with the requirements of Section V, Article 2, of the ASME Boiler and Pressure Vessel Code, except that the requirements of T-274 are to be used as a guide but not for the rejection of radiographs unless the geometrical unsharpness exceeds 0.07 in. (2.0 mm).

(A) Acceptance Standards. 
          Welds that are shown by radiography to have any of the following types of discontinuities are unacceptable:
(A.1) any type of crack or zone of incomplete fusion or penetration
(A.2) any other elongated indication that has a length greater than
(A.2.1) 14 in. (6.0 mm) for t up to 34 in. (19.0 mm), Inclusive
(A.2.2) 13t for t from 34 in. (19.0 mm) to 214 in. (57.0 mm), inclusive
(A.2.3) 34 in. (19.0 mm) for t over 214 in. (57.0 mm) where t is the thickness of the thinner portion of the weld

NOTE: t referred to in (A.2.1), (A.2.2), and (A.2.3) above pertains to the thickness of the weld being examined; if a weld joins two members having
            different thickness at the weld, t is the thinner of these two thicknesses

(A.3 ) any group of indications in line that have an aggregate length greater than t in a length of 12t, except where the
          distance between the successive indications exceeds 6L where L is the longest indication in the group
(A.4)  porosity in excess of that shown as acceptable in Nonmandatory Appendix A, A-250 of Section I of the ASME Boiler
          and Pressure Vessel Code
(A.5)  root concavity when there is an abrupt change in density, as indicated on the radiograph.


Comments

  1. Can you explain the cluster and single porosity criterias with some photos and sample drawings.

    ReplyDelete

Post a Comment

Popular posts from this blog

Important point for Welding Inspector-(SE-1)

Third Party Inspection for Pressure Vessel –

Third Party Inspection for Ground Storage Tank-

Third Party Inspection for Valve - Procedure

Pressure Vessel Inspection as per ASME SEC VIII DIV.1

Third Party Inspection for Shell and Tube Heat Exchanger-

Important point for Welding Inspector-SE-2

(Importants) ASME and National Board Stamps-